PRIORITIZE WORK

 
Canter operator must be able to effectively prioritize what to work on first, what to direct attention to and how the flow of the mill works – the focus is how to minimize the down-time of each canter line;

The main priority is keeping logs continuously flowing through both canter lines.  This is accomplished by:

  - Having a log supply at the log sorts; and

       - Logs being processed through the debarkers; and

             - Having a log supply at the debarker infeeds.


Note: If the canter operator is ever working with utility, supervisor or maintenance on a task that requires their full attention in order to complete that task safely then that item will always take priority.